Client:
Monarch Aircraft Engineering
|
Location:
London, Luton Airport
After an initial onsite consultation of the existing workshop, our highly skilled design team set to work on creating a bespoke solution to meet the air conditioning and ventilation needs of the new Training Academy.
Managed by Orbital’s Contracts Director and conducted onsite by Orbital’s Engineering Team, the installation was implemented in two phases over a three-month period.
Both Split and Multi-Split Systems were commissioned and installed.
At every single stage, the Orbital team worked carefully to SEC’s project schedule specifications, paying attention to detail and ensuring agreed timeframes were met along the way.
Upon completion, a full handover was delivered by Orbital, and at this time, full user training was provided as well as an extensive ‘Operation & Maintenance (O&M) Manual’.
Since project completion, Monarch Aircraft Engineering Ltd has entered into a five-year Preventative Maintenance Plan with Orbital Climate Solutions Ltd.